Completion:
2001 |
Service provided:
|
|
Engineering structures and traffic installations:Project
engineering design HOAI phases 1-6
|
|
Structural design: HOAI phases 1-6
|
Technology:
|
|
Construction of a new movable sluice with a R.C.
base as a high-water spillway in the upper river
Havel region
|
|
Construction of a new 15-km-long intersecting
structure in bolted pre-fabricated steel rubbing
in an open pit with closed-circuit water management
|
|
Installation of galvanised sheet piling with
accessible R.C. capping piece
|
|
Asphalting (roadway renewal in the building site
area)
|